Sunday, July 29, 2012

Build Week #13

This week there has been some good progress again and I was super excited to see that our cabinets were delivered early in the week.  I came up with designs to make changes to the standard cabinets so I was anxious/nervous to see how it all turned out.  The stain was not the correct color so that has been stressful and I am sure I won't feel good about it until they are all fixed but other than that everything looked great.  The cabinets were definitely my lowlight and highlight this week but they were also busy with:

Exterior - Ready to paint!
Kitchen - Ready for granite!
Evan's room, Family room, Resource desk AKA my office

-Tiled in the 3rd floor bonus bathroom, LVT in laundry room
-Siding just about complete
-A/C and furnace installed
-Hardwood floor installed
-Porch construction complete
-Trim/millwork installed