Saturday, June 16, 2012

Build Week #7

Not a lot of action on the exterior of the house this week but plenty going on inside. Both HVAC and plumbing in in progress. Not much to show with pictures other than our fireplace has been installed. They did bring in the drywall to the basement and have all windows installed and all of the doors with the exception of the front door. Over the next couple weeks they will continue to work on the plumbing, mechanical, and electrical.