Saturday, August 18, 2012

Build Week #16


We thought we may be getting behind schedule due to some of our tile being on back order but thankfully it was all in on Wednesday and they got right to work.  Besides finishing off most of the bathroom tile they also:

  • Installed bathroom faucets
  • Installed light fixtures
  • Caulked and sanded walls around the house where they needed to be touched up
  • Graded the lot
  • Black-topped driveway
  • Put in boulder wall landscaping in the front of the house
  • Planted all scrubs and trees


Island faucet, pendant lights, under-counter lights, cook-top & hood, and oven installed

Master bath shower and tub surround tiled