This week was exciting since instead of breaking things down we had some things actually getting fixed back up. On Monday the plumber started right finished up on Wednesday and the electrician was busy Wednesday through Friday.
Some of the tasks on their lists were:
- Installed new water heater
- Plumbing updates to both bathrooms: showers/tubs and sinks
- Added bath fan to the main floor bathroom and installed new fans in both bathrooms
- Ran plumbing to the new locations in the kitchen for sink, dishwasher, and refrigerator water line
- Added 6 canned lights
- Added ceiling lights to all bedrooms
- Added island light
- Checked all switches and outlets
- Demo electrical in walls that we removed
- Replaced the fuse box with new panel
- Installed new outlets to meet code; mostly in the kitchen
- Added new phone jack in kitchen
Other items completed this week:
- Installed furnace (by HVAC)
- Picked up special order doors; and painted all 12 doors!!
- Finished remaining demo of the family room wall after the electrical was removed
- Built breakfast bar wall
- Added insulation to the kitchen ceiling
- We also managed to fill up another dumpster bag