Monday, May 6, 2013

Flip House - Week Three

Another week in the books completed at the house on Walnut.

This week we ran into a road-block with inspections.  We called, went to the city building department, and reviewed the guidelines online to determine what permits we needed.  Our contractors pulled permits for the electrical, plumbing, and the furnace replacement however when the plumbing inspector arrived he determined that we needed another permit and placed a stop work order on our door.  This set us back a couple days.  The city was very nice about everything and said that the work we are doing is really borderline in terms of needing additional permits.  Each room individually would not need another permit but when you look at the full scope of work in the house they said we needed a permit for the remodel.  This will also require a framing inspection and an insulation inspection as well.  We want to do everything by the book so we have no problem with this.  We should be good to go to start work Monday morning.  Even though our contractors didn't work Thursday and Friday we were still busy all week and weekend.
  • Plumbing and electrical inspections
  • Prepped the demo walls for new drywall (i.e. pull out all of the nails and screws left behind from the demo)
  • Primed the basement fireplace
  • Painted bi-fold closet doors
  • Sanded, primed, and painted existing windows trim
  • Put all of the doors back on jams (removed everything to paint last week)
  • Removed all of the thinset left on the basement bathroom floor and entry way
  • Purchased additional materials including the closet shelving
  • Had another dumpster bag picked up
  • Removed all existing hardware, shelves, rods, etc. in the closets
  • Accessed yard work needed and contacted a few companies for bids to do the initial yard clean-up