The house is starting to look more like a house and we finally have running water in the bathrooms and working toilets!

From the project plan we completed:
  • Installed window casings
  • Grouted basement bathroom
  • Grouted entryways
  • Painted basement: finished painting bathroom, painted bedrooms
  • Painted upper level bath medicine cabinet
  • Painted inside of bi-fold doors and insides of closets in the upstairs bedrooms
  • Installed bathroom cabinet and mirror in basement bath
  • Cleaned out the gutters...this was another dirty job!
  • More landscaping clean-up including adding mulch to planting beds and seeding lawn where needed
This just about wraps up the work for the contractors besides the flooring, granite, and kitchen sink & faucet.  This week they were busy with:
  • Door hardware (knobs and stops) installed
  • Electrical inspection completed and passed
  • Range and refrigerator installed
  • Refrigerator water-line connected
  • Installed all of the bathroom plumbing (toilets, sinks, faucets, and shower/tub faucets)